COMPUTE ATLAS Supercomputer supply-chain graph
1153 systems 482 sites Sourced data

Supercomputers/Systems/AWE Vulcan

United Kingdom · operational · classified

AWE Vulcan

Also known as Vulcan

Operated by AWE at AWE Aldermaston .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
vendor peak
Rpeak
7.00 PFlop/s
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Cray Shasta system (Cray, an HPE company)
Hewlett Packard Enterprise - Reported globenewswire.comawe.co.uk
CPU -
2nd Generation AMD EPYC 7542 processors
AMD - Reported globenewswire.com
Interconnect -
Cray Slingshot interconnect
Hewlett Packard Enterprise - Reported globenewswire.com
Storage -
Cray ClusterStor Lustre storage, nearly 100 GB/s I/O
Hewlett Packard Enterprise - Reported globenewswire.com

The read

Named 'Vulcan' after the RAF's V-bomber, in the same naming tradition AWE uses for its HPC estate; it shares that name by coincidence with LLNL's unrelated BlueGene/Q-era Vulcan, which is why this row's page title reads 'AWE Vulcan' rather than plain 'Vulcan'. A Cray Shasta system (Cray was already an HPE subsidiary by the November 2019 announcement) built around 2nd Generation AMD EPYC 7542 processors and Cray Slingshot interconnect with ClusterStor Lustre storage, procured for the UK's Trident warhead stockpile stewardship programme. AWE's own announcement gives no exact node count or final measured performance figure; the roughly 7 petaflops figure is the vendor's pre-deployment target stated at the selection announcement, not a confirmed post-installation measurement, and no public TOP500 submission has been found for it, which is typical for UK defence HPC. It entered active service in December 2021 after site acceptance testing in spring 2021.

Timeline

Site & facility

AWE Aldermaston

Location
Aldermaston, United Kingdom
Commissioned
2021

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
awe.co.uknames system only-
globenewswire.comnames system only-

Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.

Further reading