Supercomputers/Sites/Santa Teresa Project Jupiter Campus
Santa Teresa, NM · USA
Santa Teresa Project Jupiter Campus
Operated by STACK Infrastructure. Hosting 1 system in this dataset, 0 of them currently operational.
- Systems hosted
- 1
- Installed Rmax
- 0.0 GFlop/s
- Recorded power
- 0 kW
- Cooling
- -
Facility facts
Power, cooling and efficiency figures for Santa Teresa Project Jupiter Campus, each with its own source and date.
| Fact | Value | As of | Basis | Source |
|---|---|---|---|---|
| Cooling | Closed-loop pipe system, one-time fill then recycled; average about 20,000 gallons per day, capped at 60,000 | 2025-09 | Press report | elpasomatters.orgabqjournal.com |
| Power supplier | Standalone microgrid of 700 to 900 MW of simple-cycle natural gas turbines, not connected to the El Paso Electric grid; drinking water from CRRUA | 2025-09 | Press report | elpasomatters.org |
Systems at this site
| System | Rmax | Power | First operational | Status |
|---|---|---|---|---|
| Stargate Project Jupiter (New Mexico) | - | - | - | under construction |
Facility fields are recorded only where a public source states them. Blank means we have not found one, not that the value is zero: an important distinction if you are aggregating power or PUE across sites.