Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1092 of 1153 systems have a readable citation that names them, and 40 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- 525.71 TFlop/s
- Rpeak
- 532.22 TFlop/s
- Rmax ÷ Rpeak
- 98.8%
- Cores
- 15,120
- Power
- 257.04 kW
- Per watt
- 2.0 GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - DALCO H88 cluster | DALCO | - | Reported | top500.org |
| CPU | - Intel Xeon E5-2630v4 10C 2.2GHz, 15,120 cores | Intel | - | Reported | top500.org |
| Interconnect | Omni-Path Architecture Interconnect Fat tree · 100 Gb/s per port · About 1 microsecond Intel Omni-Path | Cornelis Networks | - | Reported | top500.org |
The read
bwForCluster NEMO at the University of Freiburg, a DALCO H88 cluster of Xeon E5-2630v4 10C 2.2GHz nodes on Intel Omni-Path for neuroscience, particle physics, microsystems engineering and materials science. TOP500 lists 15,120 cores, 0.53 PFlop/s Rmax and 257 kW and ranks it 215th in June 2016, 296th in November 2016 and 390th in June 2017. The Freiburg HPC newsletter of December 2017 reports an inauguration in August 2016 and an October 2017 extension of 152 nodes to 900 compute nodes and 18,000 cores, so the TOP500 figures describe the earlier size.
Timeline
Public list appearances
Pointers only: rank and edition, linking to the canonical entry. We do not reproduce list tables. See sourcing policy.
Site & facility
Change history
- 2026-10-07 Added NEMO bwForCluster, a mid-list TOP500 system (2016-06 215)
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| top500.org | names system and part | Omni-Path Architecture |
| bwhpc-c5.uni-freiburg.de | names system only | - |
Checked 2026-10-09 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.