COMPUTE ATLAS Supercomputer supply-chain graph
1540 systems 545 sites Sourced data

Supercomputers/Systems/Elea BEL1 (Belem)

Brazil · planned · ai training

Elea BEL1 (Belem)

Also known as Elea Belem AI data center

Operated by Elea Data Centers at Elea BEL1 Site (Belem) .

Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1350 of 1540 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Elea builds and operates BEL1 with AXIA Energia supplying renewable power
Elea Data Centers
- Reported eleadatacenters.comdatacenterknowledge.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Facility power 7.5 MW 2026-06 Design target Initial capacity; up to 100 MW possible in later phases. IT versus total not stated eleadatacenters.comdatacenterknowledge.com

The read

Elea Data Centers' BEL1 in Belem, Para, announced as the Amazon region's first 'AI neutral' data center: 7.5 MW initial capacity, already backed by large anchor clients, with up to 100 MW possible in later phases and operations scheduled for the second quarter of 2027. It sits near AXIA Energia's Miramar high-voltage substation and will buy 100 percent renewable energy from AXIA under a PPA. The project grew from Belem's role as COP30 host. No accelerator vendor, count or tenant is named. Elea's much larger Rio plan is `elea-rio-ai-city`.

Timeline

Site & facility

Elea BEL1 Site (Belem)

Location
Belem, Brazil
Utility
AXIA Energia (Miramar substation)

Change history

Further reading