Supercomputers/Systems/Airbus HPC6
France · operational · hpc
Airbus HPC6
Also known as HPC6
Operated by Airbus at Airbus Toulouse (Saint-Martin) .
Researched with AI assistance, checked by scripts. These rows were researched by AI agents reading public operator, laboratory and vendor sources, appended by scripts and checked by automated validation; no subject-matter expert has reviewed them (how this site is made). A mechanical second-reader pass has since fetched every cited source: 1,350 of 1,581 systems have a readable citation that names them, and 64 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.
Measured performance
- Rmax
- -
- Rpeak
- -
- Rmax ÷ Rpeak
- -
- Cores
- -
- Power
- -
- Per watt
- - GF/W
Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.
What this machine is made of
One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.
| Role | Part | Supplier at build | Quantity | Confidence | Source |
|---|---|---|---|---|---|
| Integrator | - BullSequana XH3000 rack infrastructure, delivered by Bull (Eviden/Atos's advanced-computing business, rebranded from Eviden back to Bull in January 2026) | Eviden | - | Verified | airbus.comtheregister.com |
| Accelerator | - Nvidia GPU blades, exact model undisclosed | NVIDIA | - | Reported | theregister.com |
| CPU | - AMD EPYC, mix of Genoa and Turin generation processors | AMD | - | Reported | theregister.com |
| Interconnect | NVIDIA InfiniBand NDR (Quantum-2) Interconnect Fat tree or dragonfly+ · 400 Gb/s per port · Under 0.6 microseconds Nvidia InfiniBand NDR, 400 Gbps per port | NVIDIA | - | Reported | theregister.com |
| Storage | - IBM Spectrum Scale (Storage Scale System appliances) | IBM | - | Reported | theregister.com |
Engineering, funding and access
What Airbus HPC6 runs on, who paid for it and how people get time on it. Each line carries who said it and when.
Hardware
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Compute nodes | 1,430 nodesDerived lower bound across both sites: Bull states more than 860 compute nodes in Toulouse and over 570 in Hamburg (860 + 570 = 1,430), each with two AMD 64-core processors; Le Monde Informatique reports several hundred thousand CPU cores | 2026-05 | Vendor stated | bull.com |
| Interconnect and topology | NVIDIA InfiniBand NDR, 400 Gb/s per port | 2026-05 | Press report | theregister.comlemondeinformatique.fr |
| Cooling design | Bull Direct Liquid Cooling with warm water; heat from the system is reused to supply neighbouring buildings on the Airbus siteBull's 19 May 2026 release states direct liquid cooling and heat reuse; the warm-water detail is from Le Monde Informatique; Airbus describes a planned local heat exchange system | 2026-05 | Vendor stated | hpcwire.comlemondeinformatique.fr |
Software
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Parallel filesystem | IBM Storage Scale (Spectrum Scale) on IBM Storage Scale System appliancesNo storage capacity disclosed | 2026-05 | Press report | theregister.comlemondeinformatique.fr |
| Job scheduler | One batch scheduler sends each job to Toulouse or Hamburg according to available resources; workloads are not split across the two sitesScheduler product not named | 2026-05 | Press report | theregister.comlemondeinformatique.fr |
Funding
| Item | Detail | As of | Basis | Source |
|---|---|---|---|---|
| Stated cost | 116 USD mThe Register: close to EUR 100 million ($116 million) over five years for an all-inclusive HPC-as-a-service deal; Le Monde Informatique gives a global price of EUR 100 million | 2026-05 | Press report | theregister.com |
| Procurement | Five-year HPC-as-a-service contract with Eviden's Bull, signed in 2024 after a classical procurement won on price-performance, displacing HPE after about 24 years as Airbus's HPC supplierBull's release says the first system entered service in Toulouse in 2025, 14 months after contract signature; The Register instead says the May 2026 inauguration came 14 months after signature | 2026-05 | Press report | lemondeinformatique.frtheregister.com |
The read
Airbus's own generation-6 in-house HPC platform, internally named HPC6 by Airbus itself on its own June 2026 newsroom story, which collides with the unrelated HPC6 already in this dataset that Eni operates in Italy: this row is titled 'Airbus HPC6' to keep the two systems distinct, the same disambiguation approach already used for AWE Vulcan against LLNL's unrelated Vulcan. Delivered by Bull (Atos/Eviden's advanced-computing business, itself rebranded from Eviden back to the historic Bull name in January 2026, with full corporate separation from Atos targeted for later in 2026) as two BullSequana XH3000 sites, Toulouse (operational December 2025) and Hamburg (operational April 2026), that run as a single virtual cluster under one task scheduler rather than as two separate machines; this row records Toulouse, the first and primary site, and treats the pair as one operator-defined system. The Register and Airbus's own account agree on a roughly 100 million euro, five-year HPC-as-a-service contract, AMD EPYC Genoa and Turin CPUs, unspecified NVIDIA GPU blades, NVIDIA InfiniBand NDR at 400 Gbps per port, and IBM Spectrum Scale storage, tripling Airbus's prior simulation capacity for aerodynamics, acoustics, structural and digital-twin work including the A350 Freighter programme and next-generation helicopters. Airbus and Bull both declined to disclose node counts, GPU counts or a Linpack figure, calling them confidential, and no TOP500 submission was found, so cores, power and FLOPS are left blank and ranked is 0.
Timeline
- 2024 Airbus signed a five-year, EUR 100 million HPC-as-a-service contract with Eviden's Bull for two supercomputers, ending about 24 years with HPE source
- 2025-12 First operational source
- 2026 Delivery of the Hamburg supercomputer and its modular data centre completed the two-site programme begun in Toulouse source
- 2026-05-19 Bull and Airbus inaugurated the two-site Toulouse and Hamburg infrastructure, which Bull says triples Airbus's simulation capacity source
Site & facility
Airbus Toulouse (Saint-Martin)
- Location
- Toulouse, France
- Commissioned
- 2025
Change history
- 2026-10-01 Added Airbus HPC6 (Airbus)
Related systems
Same operator
- Airbus HPC4 · France, operational, 2014
- Airbus HP PODs · France, operational, 2011
Source check
We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.
| Cited source | Result | Found on the page |
|---|---|---|
| airbus.com | names system only | - |
| theregister.com | names system and part | NVIDIA InfiniBand NDR (Quantum-2) |
Checked 2026-10-18 by pnpm verify. Re-run it and the table changes with the web.
Further reading
Operating a supercomputer
Acceptance testing, why "installed" and "in production" are six months apart, and the machine lifecycle.
Inside a node
Latency-optimised versus throughput-optimised processors, NUMA, and the end of the host-to-device copy.
The interconnect
Topologies, why latency and tail behaviour matter more than bandwidth, and how the fabric market consolidated.