COMPUTE ATLAS Supercomputer supply-chain graph
1540 systems 545 sites Sourced data

Parts/Facility/Medium-voltage switchgear

Facility · 2000

Medium-voltage switchgear

The utility-to-building boundary. Lead times here now gate project schedules more often than silicon does.

Why this part

The place a campus's power actually enters the building, and increasingly the actual schedule constraint on a new machine. A GPU generation now arrives faster than utilities can build substation capacity or than switchgear manufacturers can deliver equipment, so procurement teams report ordering electrical gear years before the compute it will serve is even announced. Lead time here, not silicon lead time, is what most often sets the date a large AI cluster actually goes live, which is the opposite of how these projects are usually described in public.

Systems using this part

No systems in the current dataset record this part. It is carried in the taxonomy so the graph is complete, and so edges can attach to it as coverage grows.

Further reading